51 Data Center Statistics for 2026

US data center construction is growing faster than any other kind of office building. By September 2026 the monthly spending rate was close to double the total for all of 2025, and Census Bureau revenue for the hosting and data processing industry rose 22.2% in a year.

Headline figures

Jobs tell a different story. Payroll employment in the same industry has drifted down since 2023 while revenue and building have climbed. In Great Britain, metered grid electricity shows where the buildings are: one town, Slough, used 29% of all data centre electricity in 2024.

Each measure below keeps its own scope. US industry figures cover NAICS 518, which includes web hosting and cloud computing as well as data centre operators. British figures cover colocation, managed hosting and hyperscale sites, not company server rooms.

How much is the US spending to build data centers?

More every year since the Census Bureau started counting in 2014. The amount put in place grew more than twentyfold by 2025, and data centers now make up most private office construction.

$4.2bn 2016 $6.3bn 2018 $10.1bn 2020 $14.6bn 2022 $21.3bn 2023 $37.6bn 2024 $50.7bn 2025 $96.5bn 2026
View data table
Private data center construction in September of each year, seasonally adjusted annual rate, billions of dollars. The 2026 value is preliminary.
PeriodValue
2016$4.2bn
2018$6.3bn
2020$10.1bn
2022$14.6bn
2023$21.3bn
2024$37.6bn
2025$50.7bn
2026$96.5bn
Private data center construction in September of each year, seasonally adjusted annual rate, billions of dollars. The 2026 value is preliminary. (US Census Bureau (construction spending, monthly), Nov 2026)

Construction spending is the value of work put in place in the period, not the value of contracts signed. The Census Bureau files data centers under private office construction. Monthly figures are seasonally adjusted annual rates and are revised; annual totals are not seasonally adjusted. The two cannot be added together.

How much revenue does the US hosting and data processing industry earn?

Well over $100 billion a quarter. The Census Bureau's quarterly survey shows revenue growing by about a fifth a year, faster than the information sector as a whole.

These are advance estimates for employer firms, published on 19 November 2026 and subject to revision. The survey still uses 2017 industry codes, under which NAICS 518 is called data processing, hosting and related services. Revenue includes cloud and hosting services sold by firms classified here, not the revenue of every company that owns a data center.

How many people work in US data centers and hosting?

Several hundred thousand, depending on the count. The establishment census and the monthly payroll survey count jobs differently, and the payroll survey shows a fall since mid-2023 while revenue kept rising.

  1. 1 California 123,859
  2. 2 Texas 56,290
  3. 3 New York 39,730
  4. 4 Virginia 33,404
  5. 5 Florida 30,385
  6. 6 Massachusetts 27,905
  7. 7 Georgia 26,230
  8. 8 Illinois 21,934
Employees in NAICS 518210 (computing infrastructure, data processing and web hosting) by state, March 2023. (US Census Bureau (County Business Patterns 2023, states), 2025)

The 2023 census uses 2022 industry codes (computing infrastructure providers, data processing, web hosting and related services); 2019 used 2017 codes (data processing, hosting and related services), so the two years are close but not identical in scope. The BLS series is a monthly payroll survey with its own sample and is not seasonally adjusted here.

Which states have the most data center and hosting jobs?

County Business Patterns counts employees on the payroll of each establishment in the pay period including 12 March. A cloud firm's staff are counted where they work, which may be an office and not a data center building. Census flags the Virginia employment figure as having moderate noise added for confidentiality.

How much electricity do data centres use in Great Britain?

More each year since 2020, measured from electricity meters. Use is concentrated west of London: Slough and Hillingdon account for most of the growth.

3.16 2020 3.44 2021 3.84 2022 4.13 2023 4.46 2024
View data table
Grid electricity used by data centres in Great Britain, TWh, 2020 to 2024. Metered estimates (official statistics in development).
PeriodValue
20203.16
20213.44
20223.84
20234.13
20244.46
Grid electricity used by data centres in Great Britain, TWh, 2020 to 2024. Metered estimates (official statistics in development). (DESNZ (data centre electricity workbook), Jun 2026)

DESNZ matched meters to a list of 242 identified data centres. The figures exclude enterprise data centres that a company runs for its own IT, and a data centre counts as operational in a year when at least one meter could be matched to it. The share of all grid electricity is on the green hosting page.

See also: Energy and carbon of hosting

How much data centre capacity does the UK have?

Under 2 GW of IT load in 2024, on government estimates. Its scenarios expect demand to outgrow supply by 2030, mostly because of AI.

IT load is the power drawn by servers, storage and network equipment, not the whole site including cooling. The DSIT scenarios build on McKinsey demand and supply modelling and are projections, not counts. They measure capacity, while the DESNZ figures above measure electricity actually used, so the two are not comparable.

What is the EU planning for data centres?

More capacity, with a label for each large site. The Commission adopted a rating scheme in September 2026 that will cover individual data centres above 500 kW.

The Commission's full report on data centre energy efficiency and the first results of the Energy Efficiency Directive reporting scheme sit on energy.ec.europa.eu, which could not be reached for this page. The EU energy figures from the press release are on the green hosting page.

Glossary

NAICS 518 / 518210
The US industry code for computing infrastructure providers, data processing, web hosting and related services (called data processing, hosting and related services before 2022).
Seasonally adjusted annual rate
A monthly value adjusted for normal seasonal swings and multiplied up to show what a full year at that pace would total.
Colocation
A data centre that rents space, power and cooling to customers who bring their own servers.
Hyperscale
Very large data centres run by major cloud and technology firms.
IT load
The electrical power drawn by computing equipment, measured in megawatts (MW) or gigawatts (GW).
TWh
Terawatt-hour, one billion kilowatt-hours of electricity.
DESNZ / DSIT
The UK Department for Energy Security and Net Zero and the Department for Science, Innovation and Technology.

Methodology and sources

Figures come from US Census Bureau County Business Patterns, the Quarterly Services Survey and construction spending tables, the BLS Current Employment Statistics survey, DESNZ statistics on data centre electricity in Great Britain, the DSIT Compute Evidence Annex and a European Commission press release. Each figure links to the file or report that carries it, with the date. Employment counts from the establishment census and the payroll survey are kept apart, as are annual and seasonally adjusted monthly construction spending, and metered electricity is kept apart from capacity. Shares, changes and pay per employee are our own sums and are marked as calculated. The IEA, Lawrence Berkeley National Laboratory and Uptime Institute sites blocked automated downloads, so their estimates are not used. The page is reviewed monthly and updated when a producer releases newer data.